Majority
Headnote
Contract for State or City Work—Claims for Materials and Labor —Construction of Statute—Maturity of Action upon Bond.— The act of March 27, 1897, which provides for the filing of verified claims for materials furnished or labor done for the contractor under a contract for building, excavation, or other mechanical work for the state, or for any city, is distinct from and independent of the general mechanics’ lien law, and the surety on the contractor’s bond provided for in the act, may be sued by a material-man or laborer, as soon as the contractor may be sued by them, provided the claim is filed within thirty days after the debt is due from the contractor; and the debtor is not required to wait for the final completion of the work by the contractor.Plaintiff’s complaint sets forth three causes of action upon a bond executed by defendant Powell, as principal, and defendant company, as surety, under the provisions of the act of March 27, 1897, (Stats. 1897, p. 201). It is alleged that Powell entered into an agreement with the city of Los Angeles on February 8, 1899, to construct a tunnel in Third Street, from Hill to Flower Street, and to furnish at his own cost all the labor and material necessary therefor, and that said work was never completed; that defendants entered into a written undertaking as provided for in the above act. For a first cause of action it is alleged that plaintiff furnished the said Powell the work of certain teams during the months of July, August, and September, 1899, at an agreed price per day for each team and man, amounting in value, in all, to $514.75, and that said work of said teams was completed on the ninth day of September, 1899; that all said work was “furnished for and actually used in the construction of said tunnel under said contract,” and that on March 19, 1900, plaintiff filed with said council a verified statement of his said claim, with a statement that the same had not been paid.
A second cause of action sets forth that one Clapham performed labor for said Powell as a blacksmith during the same months as above named, at the agreed price of three dollars per day, amounting in all to $154; that his said work was completed September 6, 1899, and that said labor was performed in the construction of said tunnel under said contract; that said Clapham filed a verified statement of his said claim with said council on March 19, 1900, and on the same day assigned to plaintiff his claim as aforesaid and all his rights against the defendant- company.
For a third cause of action, and by similar allegations, plaintiff sets forth the claim of one French for one day’s labor, in the month of July, 1899, as superintendent of the work on said tunnel, at the agreed price of $2.50; alleges the filing of the claim and its assignment the same as in the case of said Clapham. Appended to the complaint are copies of the itemized claims filed with the council.' Defendants answered, controverting the allegations of the complaint, and, as a separate defense, pleaded the act in bar, alleging that notice of the several claims was not filed within the time re
1. Apellants contend that the suit is prematurely brought, for the reason, as appellants construe the terms of the act, that the claims must be filed within thirty days after the completion of the whole work. In other words, that the expression, “shall within thirty days from the time such work is completed,” etc., fixes the beginning and the ending of the time within which the claim must be filed.
On the other hand, respondent contends “that this language was meant simply to set a limit of time after which such claims could not be filed, and not to forbid the filing of a claim before the completion of the whole work, provided the claimant’s demand is past due.” Section 1 requires that— “Every contractor ... to whom is awarded a contract for the . . . performance of any building, excavating, or other mechanical work for this state, or by any . . . city . . . therein, shall, before entering upon the performance of such work, file with the . . . common council . . . a . . . bond ... in a sum not less than one-half of the total amouiit payable by the terms of the contract; such bond shall be executed [prescribes by whom], and must provide that if the contractor . . . fails to pay for any materials or supplies furnished- for the performance of the work contracted to be done, or for any work or labor done thereon of any kind, that the sureties will pay the same, . . . provided, that such claims shall be filed as hereafter required. ’ ’ Section 2 provides that “Any material-man, . . . furnishing materials, . . . used in the performance of the work, ... or any person who performed work or labor upon the same, . . . whose claim has not been paid, . . . shall, within thirty days from the time such work is completed, file with the . . . common council ... a verified statement that the same has not been paid. At any time within ninety days after the filing of such claim, the person . . . filing the same may commence an action against the sureties on the bond, specified and required by section 1 hereof.”
Appellants’ argument is that the act must receive the same construction as was given section 1187 of the Code of Civil
The construction we would give the word “within” is not unusual or strained, as will be seen from cases cited by respondent. “ Within ten days after service” of a notice of a
As there was reason for putting a different construction on the word “within” in respect of filing mechanics’ liens, because of the provisions of section 1194, so, also, is there reason for the construction we give to the word as used in the act before us. It had been held that liens could not be enforced against public property, and the legislature, probably for this reason, enacted the law of March 27, 1897. But the act is entirely distinct from and independent of the general mechanic’s lien law, and no clause in it indicates that the right to proceed under it by any creditor of the contractor, protected by the bond, is subject to a condition that he must wait the final completion of the work, which may be long delayed, and, as in this case, is not yet completed; and nothing in the statute indicates that he may then only recover a share of the fund in the proportion that his claim bears to all the claims against it. The bond must be for an amount not less than one half the contract price for the work, and the publicity of the bond and the filing of claims are notice to persons dealing with the contractor and of the extent of his
2. The question next presented is as to who is liable to plaintiff on the claims the subject of the action. Appellants contend that Powell is not liable, because the findings show that the services were rendered at the request of Chaffey, who was sub-contractor under Swenson & Hill, the assignee of Powell. The bond refers to the contract entered into by Powell with the city, and makes it a part of the bond. The condition of the bond is, that “the above bounden principal [Powell] shall pay or cause to be paid for all work and labor done thereon, of any kind, and for all material and supplies furnished for the performance of said work; ... if the said principal shall fail to pay for any materials or supplies furnished for the performance of the work contracted to be done, or for any work or labor done thereon of any kind, that the said sureties will pay the same in an amount not exceeding the sum hereinbefore specified” ($44,225), etc. The contract contained the following provision (par. 7): “The contractor will not be permitted to sublet any portion of the work without the consent of the city engineer, and whenever such subletting is permitted the party performing the work will be considered as the agent of the contractor; the latter will be held responsible for all indebtedness incurred by the said agent on account of the work.” We do not think that Powell
3. It is next contended, as to the first cause of action, that as plaintiff performed no labor, and as he furnished a teamster, two horses, and a scraper to Chaff ey, the claim should have been made by the teamster, and not by plaintiff, and as this was not done, there is no action against either Powell or the Surety Company. The engagement for the labor of the teamster, horses, and scraper was with plaintiff, for which a gross sum per day was to be paid for the outfit. Plaintiff looked to Powell, and not to Chaffey, and, as we have seen, the contract and bond warranted this, and it was immaterial whether he did the work with his own hands. As to Clapham’s services as blacksmith, appellants claim that it was not the kind of labor contemplated by the act, and was not the kind of labor for which a mechanic’s lien will be permitted (citing McCo
We advise that the judgment be affirmed.
Cooper, C., and Gray, C., concurred,
For the reasons given in the foregoing opinion the judgment is affirmed. Harrison, J., Garoutte, J., Van Dyke, J.
Cases cited
- Roylance v. San Luis Hotel Co. 74 Cal. 273 p. 640
- Willamette Steam Mills Lumbering & Manufacturing Co. v. Los Angeles College Co. 94 Cal. 229 p. 640
- Bates v. County of Santa Barbara 90 Cal. 543 p. 640, p. 642
- Bianchi v. Hughes 124 Cal. 24 p. 640
- Sweeney v. Meyer 124 Cal. 512 p. 640
- Newport Wharf & Lumber Co. v. Drew 125 Cal. 585 p. 640
- First Nat'l Bank of Bridgeport v. Perris Irrigation Dist. 107 Cal. 55 p. 642
- McCormick v. Los Angeles City Water Co. 40 Cal. 185 p. 644
- Wilson v. Nugent 125 Cal. 280 p. 644
- Adams v. Burbank 103 Cal. 646 p. 644
- Malone v. Big Flat Gravel Mining Co. 76 Cal. 578 p. 644