Majority
Headnote
Mechanics’ Liens — Building Contract — Abandonment bt Contractor — Amount Applicable to Liens — Bule Prior to Code Amendment. — Where a building contract had been abandoned by the contractor prior to completion of the work, the portion of the contract price applicable to the liens of other persons than the contractor was, prior to the repeal of section 1200 of the Code of Civil Procedure in the year 1911, the difference between payments made to the contractor and the value of the work and materials done and furnished at the time of such abandonment, including materials then actually delivered on the ground, “estimated as near as may be by the standard of the whole contract price,” and not by the actual value of such work and materials.Fourteen separate complaints were filed to enforce mechanics and materialmen’s liens, and by order of the court were consolidated and tried in one action. The plaintiffs in eleven of these several complaints are respondents and the appeal is here under the above title. Judgment was entered in favor of plaintiffs and from this judgment defendants appeal.
Defendants Condon and McGlynn were the contractors for the work; certain named persons defendants were owners of the property on which the building in question was erected, and defendant Dunne Investment Company was the owner of a lease executed by said owners, and erected said building in compliance with the terms of said lease. The building is situated on the northwest corner of Stockton and Ellis Streets, San Francisco.
The complaints were filed in the latter part of the year 1909 and were brought to issue by answers in 1910 and, on January 4, 1912, came on for trial, and findings of fact and conclusions of law were made on June 27, 1912, and judgment was entered on that day. Notice of appeal was served and filed July 27, 1912. Transcript on appeal was filed in the supreme court May 15, 1914. Appellants’ brief was filed September 15, 1914, and respondents’ brief was filed May 11, 1915. The cause was transferred to this court and papers filed here December 17, 1915, and appellants’ reply brief filed here January 18, 1916. It thus appears that more than two years expired after the actions were commenced before they were brought to trial. Nearly two years elapsed thereafter before transcript was filed in the supreme court. A year more passed before respondents’ brief was filed, and appellants’ reply brief was not filed until January 18, 1916, at which time the cause was submitted. We take the liberty of calling attention to the record as typical of many cases coming by transfer to this court as showing that the delay in reaching judgments on appeals in many cases is not, as is popularly believed, the fault of the appellate courts, but of the attorneys in the cases, brought about by stipulations which the courts feel bound to respect.
The attack is first made upon the finding upon which the judgment is based for the reason that it ignores the element of proportion to the whole contract price; that the evidence is insufficient “to sustain the finding even as to the amount
The contract price for the building was $52,750, and the contract, with its plans and specifications, was duly recorded before the work was commenced. Work commenced under this contract October 26, 1908, and continued until July 15, 1909. The contractors being unable to complete the building, the Dunne Investment Company gave three days’ notice, as provided in the contract, to furnish the necessary labor and materials to finish the building, which the contractors being unable to do, the Dunne Investment Company employed one Charles Wright to complete the job. The contractors had received, when they abandoned the work, $31,-397.50. The liens filed amounted to about twelve thousand dollars.
The contract provided that payments for the work should be made on the first of the month “as the work progresses, in installments, based upon the. monthly estimates of all work done and material furnished and paid for in the building, up to and including the last day of the preceding month, in sums equal to seventy-five per cent of the value of said work done and material furnished, to be estimated by the architect, provided that no more than seventy-five per cent of the whole contract price shall be paid up to the time of the completion. ’ ’ There was the usual provision deferring payment of twenty-five per cent. “The monthly estimates of the architect, however, subject to correction by him in any subsequent monthly or in his final estimates. Serving merely as a basis for payments on account they are presumed to be only approximate. ’ ’
Finding 10 is as follows: “That the value of the work and materials already done and furnished by said Condon and McGlynn on July 15, 1909, under said contract, including materials then actually delivered or on the ground, estimated by the standard of the-whole contract price, under said contract, was and is $41,863.33.”
The court found that there was the sum of $10,465.83 subject to the various liens, being the difference between the amount of the work and materials done and furnished, namely, $41,863.33, and the amount paid to the contractors,
It is well settled that, prior to the revisory statute of 1911 (Stats. 1911, p. 1313), under section 1200 of the Code of Civil Procedure, the actual value of the work and materials is not the test, but the value “estimated as near as may be by the standard of the whole contract price.” (Hoffman-Marks Co. v. Spires, 154 Cal. 111 , [ 97 Pac. 152 ] ; Duffy Lumber Co. v. Stanton, 9 Cal. App. 38 , [ 98 Pac. 38 ] ; Olson-Mahoney etc. Co. v. Maxwell, 18 Cal. App. 668 , [ 124 Pac. 100 ].)
Appellants contend that the value of the work and materials as found by the court represented the actual value and not the value estimated by the standard of the whole contract price, and that the court reached its estimate by a mathematical calculation, to wit, by dividing $31,397.50, the amount paid the contractors, by .75, thus giving exactly the sum found, namely, $41,863.33. “Other than this mathematical calculation,” it is claimed, “there is not a word of evidence to sustain the finding.”
Witness Applegarth was the architect of the building and made the estimates of the work as it progressed and issued certificates therefor. He testified “that $31,397.50 was three-fourths of the. value, or possibly a little less than three-fourths of the value, of the portion of the work done by the Condon-McGlynn Company on the Dunne Building, estimated by the contract price for the whole. We were conservative always so as not to overstep the limit. So I am sure that .it was not more than three-fourths of what they had done estimated by the price of the whole.” Again, he testified: “These certificates were our estimates of the value of the work done in the period covered by the certificate estimated by the contract price.” Again: “We issued our certificates on the basis, of three-fourths of the value of the work done estimated by the whole contract price.” He testified that he helped superintend the construction of the building, and was at that time more familiar with the cost of the work required to be done on the building than at the
Witness Charles Wright, who took the contract to complete the building, testified that the actual value at abandonment was $32,850. The testimony of this witness on cross-examination showed that he underestimated the cost of different parts of the work very materially, and that his figures given for various items entering into the cost of completing the building were unreliable, and for reasons shown his estimate of such cost did not represent the reasonable cost of completing the building under the original contract. It was alleged by defendants, in their verified answer to each of the complaints, that they had paid to the contractors “a sum equal to 75% of the value of said work done and material furnished as estimated by the architect, and that the said sum was at no time more than 75% of the value of the work and materials already done and furnished, estimated by the standard of the whole contract price,” and that the amount so paid was as already stated. Appellants say as to this averment in their answer that it “is not binding, in view of the fact that the evidence, as a whole, establishes that these payments were in reality 75% of the value of the amount actually in the building.”
Section 1200 of the Code of Civil Procedure directs that the value of the labor and materials done and furnished at the time of abandonment shall “be estimated as near as may
It is further claimed that the court failed “to find the value of the work left undone” which, it is insisted, was essential “in estimating the amount subject to liens in eases where the contractor has not finished his contract.” We understand our supreme court to have held that a finding as to the cost of completing the building is not necessary. (Scheerer & Co. v. Deming, 154 Cal. 138 , [ 97 Pac. 155 ] ; Ganahl Lumber Co. v. Weinsveig, 168 Cal. 664 , [ 143 Pac. 1025 ].) In the Scheerer case, the court said it was proper as matter of evidence, to consider this fact in determining what the value is. We must presume that the court did consider the evidence before it on this fact.
We come now to the attack made upon the several claims separately.
The objections raised to this claim are: 1. That the complaint does not state a cause of action in this: (a) it shows that the lien was filed too late; (b) that it does not allege the value of the labor and materials in the building and on the ground at the time of the abandonment, based on the whole contract price, or contain “even an allegation of a fund subject to liens”; (c) the complaint “fails to allege that the lien contained a statement of the terms, time given, and conditions of the contract,” as required by section 1187 of the Code of Civil Procedure. 2. That finding No. 6 is contrary to the admissions in the pleadings. 3. That the lumber charged for was used for concrete “forms” and did not form part of the building. 4. That there is a material variance between the complaint and lien, between the complaint and the evidence, and between the lien and the evidence.
It was alleged in the complaint that, on July 20, 1909, the “said contract was abandoned before the completion thereof and there was on said date an entire cessation of labor upon said unfinished contract and upon said unfinished building or structure” and, on said date, the defendant Dunne Investment Company entered into the occupation of said building and ever since has been and now is in the use thereof; that said, cessation from labor upon said contract and upon said unfinished building or structure and said use and occupation of said unfinished building by said owner, Dunne Investment Company, continued for a period of thirty days and at the time of said cessation from labor there was in the hands of defendant, Dunne Investment Company, after deducting the payments actually due and made under said contract for the value of the work and materials already furnished, estimated according to the whole contract price, sufficient to pay the claim and lien of the plaintiff herein. ” It is alleged that the notice of lien was duly verified and recorded December 14, 1909, and is made part of the complaint “and was filed within the time allowed by law.” It is also alleged that no notice of the cessation of work on the building or of abandonment of work was ever filed in the office of the recorder.
The court found that there was an entire cessation of labor on the building on July 18, 1909, and that there never had been any notice of cessation of labor filed for record.
Appellants say: If the allegation is true that there was a cessation of labor for thirty days after July 20, 1909, as alleged, the time for filing liens would commence to run August 19th, and the right to file a lien would at most expire ninety days thereafter. Hence the complaint did not state a cause of action because, as therein stated, the lien was filed December 14th. Attention is also called to the allegation in the complaint that defendant entered into occupation and use of the building on July 20, 1909, which, it is claimed, brings the case directly within Robison v. Mitchel, 159 Cal. 581 , 591, [ 114 Pac. 984 ].
While the court found, as alleged in the complaint, that there was a cessation of labor on July 18, 1909, it found, as we have seen, that no notice thereof had been filed of record, and the court also found that there was no cessation of labor for thirty days on said building and the same was completed November 16, 1909. This plaintiff filed its lien on December 14, 1909, and was in time, if we may follow the findings of the court instead of the averments of the complaint. In considering this and other of the objections, it is to be noted that there was no demurrer to the complaint, no motion for non-suit upon the close of plaintiff’s testimony, and no motion made for a new trial. In defendants’ answer it was alleged that the contractors abandoned the work on July 15, 1909, “whereupon the said defendant entered upon the said work, excluded the said Daniel E. Condon and Chas. J. McGlynn and their men and forthwith proceeded to procure other materials and labor and entered into another contract for said work, to wit: a certain contract with one Charles Wright,” who agreed to complete the building according to the plans and specifications of the original contract. This contract was dated August 4,1909, in which the contractor agreed “to enter upon the performance of the work on the 5th day of August,
The complaint alleged as follows: “At the time of said cessation from labor, there was in the hands of the defendant, Dunne Investment Company, after deducting the payments actually due and made under said contract for the value of the work and materials already done and furnished, estimated according to the whole contract price, sufficient money to pay the claim and lien of the plaintiff herein.” It is now urged against the sufficiency of this averment that it does not allege that defendant had “any fund subject to liens.” Defendant states in its brief “it may be that this plaintiff intended to allege that it had in its hands and subject to liens sufficient money to pay the claim, but the complaint does not say so.” Had plaintiff’s failure to express its intention been pointed out by special demurrer no doubt the additional allegation would have been made. The record shows, however, that the fact here omitted constituted one of the issues tried without objection, which we think cured the defect.
The objection that the complaint “fails to allege that the lien contained a statement of the terms, time given and conditions of the contract,” as required by section 1187 of the Code of Civil Procedure, is, we think, satisfactorily met. In the first place, the lien was admitted in evidence without the objection now urged being made. The complaint alleged that the notice of lien was filed, giving the date, and that it ‘ ‘ contained, among other things, a description of the property thereby sought to be charged, as hereinbefore set forth, a statement of the names of the owners or reputed owners of said land and building or structure, to wit: [giving the names] . . . and said notice • also contained a correct statement of the demand of plaintiff for said materials furnished after deducting the just claims and offsets. ” It is then stated that the notice was duly recorded and reference is made to it and it is made part of the complaint. The lien contains a statement of the terms, time given and the conditions of the contract. The complaint and notice of lien must be read together as the latter is distinctly made part of the complaint. (Newell v. Brill, 2 Cal. App. 61 , [ 83 Pac. 76 ]; Coss v. MacDonough, 111 Cal. 662 , [ 44 Pac. 325 ].) In the absence of a demurrer, and in view of the fact that no objection was made to the introduction of the lien in evidence, and that
It is objected that there is a variance between the complaint and the lien, the complaint and the evidence, and between the lien and the evidence. The lien states that the contractors “requested claimant to furnish lumber and mill work for said building and agreed to pay for the same upon its delivery; that claimant, at the special instance and request and in accordance with the agreement of said [contractors] furnished lumber and mill work for said building on the dates hereinafter mentioned to the amount and extent presented by the various sums set opposite the respective dates, viz.”: (Then follow the items showing date, quantity of material and mill work and price.) “No time was given and there were no other terms or conditions of the said contract.” It is then stated that claimant performed its agreement “and supplied said lumber and materials as specified herein and said materials are of the reasonable value of $2,902.99, and the same were actually used in, upon and about said building.” The complaint alleged that, for said lumber and mill work, the contractors “agreed to pay the plaintiff the reasonable value thereof, in cash, and upon the delivery of said lumber and mill work; that no time was given and there were no other terms or conditions to said contract except such as the law implies; . . . that the reasonable value of said lumber and materials is set opposite the respective dates as follows”: (Then follow the items as in the notice of lien.) The evidence showed that the lumber was sold at a fixed price agreed upon with the contractors. “That the lumber and mill work furnished by the Olson-Mahoney Lumber Company for the building in question were furnished at the reasonable market price prevailing at San Francisco at the time the lumber and mill work were furnished. ’ ’ The introduction of the lien was objected to “on the ground that there is a variance between the evidence and the lien.” In the decision rendered by this court in Barrett-Hicks Co. v. Glas, 14 Cal. App. 289 , [ 111 Pac. 760 ], it was said in the opinion by Mr. Justice Hart: “The object of the statute in requiring the conditions and terms of the contract to be set forth correctly in the notice of lien is to ‘inform the owner as to the extent and nature of a lienor’s claim, to facilitate investigation as to its merits.’ . . . And the test as to the sufficiency of the notice with re
In the present case it seems to us that anyone reading the notice of lien would see that the agreement was that the materials were to be paid for, upon delivery, in accordance with the prices carried out against the various items, and that the materials were of the reasonable value as in the notice set forth, for it states that reasonable value was as the price shown. The complaint stated that the agreement was to “pay the plaintiff the reasonable value thereof, in cash, and upon the delivery of said lumber and mill work.” The evidence was that the prices were both the market value and the reasonable value as well as that the agreement was to pay a price agreed upon. We do not think that the notice of lien was insufficient, nor do we think there was any variance as claimed by appellant such as would justify a reversal of the judgment. (See Blanck v. Commonwealth Am. Corp., 19 Cal. App. 720 , 726, [ 127 Pac. 805 ], and cases there cited.)
It is next objected that the lumber furnished by plaintiff was used for concrete “forms” which did not enter into or become a part of the building and hence no lien attached. Appellant rests its point in its opening brief upon the case of
The evidence was that this building could not have been erected without the use of lumber made into forms into which the concrete was poured there to remain until thoroughly “set,” that is, for a period requiring, as the evidence showed, from fifteen to twenty days. The lumber was then removed
In the case of Pacific Sash and Door Co. v. Bumiller, 162 Cal. 664 , 667, [ 41 L. R. A. (N. S.) 296 , 124 Pac. 230 ], where materials were furnished for the alteration of a building, it was held: “Lard-oil applied to the threads of joints of pipe used in the structure, insulated or covered electric wire used for drop lights attached thereto, paste for soldering joints, asbestos comprising a part of the electric switch-board, all constitute parts of the structure and a lien may be asserted therefor. Some soapstone was used on the inside of pipes, as a lubricant, to facilitate the pulling of wires through the pipes. This, being a part of the work of construction, we think it may also be considered as a part of the material used in construction, for which a lien may be claimed.” Soapstone as a lubricant constituted “no part of the materials of which the building was constructed,” as was the test in the Stimson Mill do. case, supra, but it “was material used in the construction” of the building which was the test in the Pacific Sash & Door ca.se, supra, and should, we think, be the test here. In thus holding we are but applying the familiar rule that the language of a statute must be construed so as to adapt it to changing conditions the result of improved methods and the progress of inventive arts. In its reply brief
B. P. Avery & Sons v. Woodruff, 144 Ky. 227 , [ 137 S. W. 1088 , 36 L. R. A. (N. S.) 866 ], was a consolidated case in which it was agreed as to one of the claims that of the lumber used in forms for the concrete building being erected, “nothing remained of any of said lumber but about 10 per cent, which was in a cut-up, sawed-up, and dirty condition, such remnants being the molds (forms) knocked to pieces.” The Kentucky statutes provide: “A person who performs labor or furnishes materials in the erection, altering, or repairing a house, building, or other structure ... or for the excavation of cellars ... or for the improvement in any manner of real estate . . . shall have a lien thereon.” The court said: “If the lumber had been furnished to make a scaffold, molds, or forms, with the intention of using them in the erection of that building, and then carry them away and use them in constructing other buildings, then no lien would attach, as they would be regarded as a part of the appliances of the workmen, and would occupy the same place as a hammer, saw, or other tool used by the workmen, for which no lien is allowed by the statute (some states do, however, allow liens for scaffolds). These appellees furnished material to be used in the erection of a building which was as necessary as the sand, cement, water, or other material. In fact, the building could not have been erected without lumber to be used for the purpose for which
Further pursuit of the question is deemed unnecessary. We do not think a general rule could be safely stated to govern all cases where lumber is used in making forms for concrete work in the construction of work contemplated by the mechanics’ lien law. Each case must be governed by its own fact. This much, we think, however, can be said, and it is as far as the exigencies of the present case require; that, under the circumstances or facts shown, plaintiff is entitled to a lien for the materials it furnished and the mill work necessary for the preparation of such materials for use.
WESTEEN BUILDING MATEBIAL COMPANY’S CLAIM.
To this claim it is objected: 1. That the first two counts are contradictory, the first alleging an abandonment for thirty days, on July 14, 1909, and the filing of a lien on September 15; 2, the second alleging that the contractors (not the defendant) completed the building and that the lien was filed December 2, 1909. As to the first count it is pointed out that the court found against the cessation of labor for thirty days and hence the lien was prematurely filed; as to the second count no cause of action is stated “because there is no attempt whatever to allege a fund subject to lien”; that there is a material variance between the complaint and the lien and between the complaint and the evidence.
Respondent calls attention to the fact that the complaint was filed prior to the decision in Robison v. Mitchel, 159 Cal. 581 , [ 114 Pac. 984 ], under such decisions as Johnson v. La Grave, 102 Cal. 324 , [ 36 Pac. 651 ], holding that the contract was deemed abandoned when there had been a cessation
It is true that the findings are contrary to the allegations of the complaint: (1) That there was an abandonment of work for thirty days on July 14, 1909, and (2) that the building was completed by the contractors. The court found against the averment as to cessation of work and also found that the building was completed by defendant and not by the contractors. But this was in strict accord with the averments of the answer many times repeated, and in accord with averments in the complaints in the consolidated action. No pretense was made at the trial that the contractors completed the building, and it was not disputed at the trial that there was not a cessation of work for a period of thirty days. We do not think that contradictory averments in or statements not true in the complaint when at variance with the findings should be held fatal to recovery, where the answer cures the contradictions or misstatements, and the findings are as alleged by the answer supported by uncontradicted evidence. Allegations omitted or defectively stated may be cured or supplied by the defendant in its answer. (31 Cyc. 714; Bliss on Pleading, 437; Donegan v. Houston, 5 Cal. App. 626 , 632, [ 90 Pac. 1073 ]; Shively v. Send-Tropic etc. Co., 99 Cal. 259 , [ 33 Pac. 848 ].) It would be a vain thing to reverse the judgment on these grounds in order that the respondent might amend its complaint to harmonize with what the answer admits. It is quite obvious that the alleged variance did not mislead the defendant to its prejudice.
In this respondent’s complaint there was a failure to allege a fund subject to liens. Respondent meets the objection by resort to allegations found in other complaints and by the considerations set forth under the Olson-Mahoney claim. This, we think, under the rule governing in a consolidated action, was allowable. This rule we understand to be that the effect of the order of consolidation is to unite the causes of action so as to constitute one cause of action and one pleading, and that allegations in one complaint will remedy defects and supply omissions in another.
It is further urged that there is a variance between the complaint and the lien. The point is that the complaint relied on a contract for recovery. The averment is: “That the following is a statement of the terms, time given and conditions of the plaintiff’s contract under which it furnished said building materials, to wit: Said Condon-McGlynn Company while working on said building or structure ordered from plaintiff, for use in said building, and delivered the same and charged therefor the actual value and market rate thereof.”
The lien sets forth the character of the materials and their value and that no part of the same has been paid, etc.: “That the following is a statement of the terms, time given and conditions on which, said building material was furnished, to wit: From time to time while said Condon-McGlynn Company were engaged in the construction of said' building its duly authorized agent ordered from claimant for use in said building said material, to wit: Said crushed rock, and claimant furnished and delivered the same upon the order of said Condon & McGlynn Company and charged therefor the sum of six hundred and fifty dollars. ’ ’
The lien says nothing about a contract, but the law implied a promise to pay. The complaint stated the facts the same way, but chose to say that the terms, time given and conditions of the contract were, etc., and it then follows the lien.' "We cannot assume that the pleader meant a contract other than such as would be implied from the facts stated.
FORD AND MALOTT CLAIM.
The only objection urged to this claim is that the allegation as to the work done and materials on hand at the cessation of work is insufficiently stated. What has been said in the preceding cases upon the point applies here.
As to this claim, it is alleged that there is a material variance between the claim of lien and the evidence and that its statements are inconsistent in this — “it alleges that 2042% barrels of cement were furnished, which at $1.75, the contract price, would be $3,574.37%. But the lien alleges that the reasonable value was $3,849.68.”
The lien states that respondent “furnished materials consisting of 2042% barrels of standard Portland cement of the reasonable value of $3,849.68, to be used,” etc., under a certain written agreement. “Price. One dollar and seventy-five cents ($1.75) per barrel f. o. b. cars at factory.” Shipments to be made “in carload lots as ordered by buyer.” It was stated that “three hundred and seventy-five pounds net of cement, packed in four bags constitute a barrel”; that• the seller would pay five cents for each bag returned to the factories in good condition; seller to pay freight on returned bags; that no part of said $3,849.68 has been paid except the sum of five hundred dollars, and there are no offsets except $29.25 due to said contractors for sacks returned, and there is now due and unpaid the sum of $3,320.43, etc.
The testimony was "that respondent delivered to the contractors 2042% barrels of cement under the contract; “that the total price of the same was $3,849.68; that the reasonable value of said cement was $3,849.68.” It appeared that 722% barrels were furnished not at the factory, as the contract called for, but from a warehouse in San Francisco, where respondent had it in storage; that the contractors were charged for all the cement at the rate of $1.75 per barrel except as to the 722% barrels there was added the freight from the factory to the city, $114.56, and warehouse charges, $16.25, and five cents each for 2042 sacks, $144.50; that the. 722% barrels were furnished from the warehouse at the contractors’ request “and they agreed to pay therefor the contract rate of $1.75 per barrel plus the freight, warehouse charges and five cents for each sack. That 2042% barrels was all the cement ordered by the Condon-MeGlynn Company “and it was up to standard in every respect.” The witness testified that there was due at the commencement of the suit $3,320.43, from which should be deducted for sacks returned $479.20, leaving due $2,841.23. It thus appears that respond
WILLIAM CRONAN CLAIM.
The point made is that the allegation of the complaint is insufficient to support the judgment under section 1200 of the Code of Civil Procedure. This allegation is as follows: “That at the time of said cessation from labor upon said unfinished, contract and said unfinished building or structure, there was in the hands of the said defendant, Dunne Investment Company, after deducting the payments actually due and made on said contract between said defendant, Dunne Investment Company, and Daniel B. Condon and Charles J. McGlynn, as hereinbefore alleged for the value of the work and materials then already done and furnished, estimated according to the whole contract price, sufficient money to pay the claim and lien of plaintiff herein.”
Whatever of insufficiency there may be in these averments it was cured by sufficient allegations in other complaints. It is further contended that the claim as allowed of $2,179.50 must be reduced to $1,714.
In alleging the value of the work which had been done, as stated in the first count, the complaint, it is claimed, omitted the element of proportion to the contract price, as also the amount paid; that the complaint alleged that, on July 12, 1909, the contractors “ceased the construction of the building or structure and never thereafter resumed the construction thereof,” and there is.no allegation of completion. But it was alleged that the lien was filed December 7, 1909, more than 120 days from the time of the cessation of labor as alleged. As to the second count in this complaint, it is claimed that there is no allegation of any fund as required by section 1200 of the Code of Civil Procedure.
These averments of the complaint as to the fund were not challenged for insufficiency. The facts as we have seen as to the cessation of labor, the taking over of the work by defendant soon thereafter, and the completion of the building are all hereinbefore pointed out ’and, as we understand the decisions, all the plaintiffs may have the benefit of them.
•THE VERMONT MARBLE COMPANY CLAIM.
It is claimed that the first count of the complaint does not state a cause of action for the reasons urged to the complaint in the case of William Cronan. It is also objected to the second count of the complaint that it “does not allege that the lien contained a statement of the terms, time given, and conT ditions of the contract.” The complaint states that the notice 'of lien was duly recorded, giving the page of record, and the lien was made part of the complaint and contained a full statement of the terms, time given, and conditions of the contract, and was received in evidence. It is true that the complaint does not set forth the terms, time given, and conditions of the contract, but it referred to the notice of lien, and alleged that it contained “a correct statement of the demand of plaintiff for said labor performed and said materials furnished after deducting all just credits and offsets” and, as remarked above, the lien was made part of the complaint.
Appellant relies upon Davis v. Treacy, 8 Cal. App. 395 , [ 97 Pac. 78 ], Very properly the court said in that case: “The complaint is at least unique.” It was held insufficient, on
In the present case there was no demurrer to the complaint. The only objection to the lien as evidence was that there was a material variance between the lien pleaded and that the lien was filed too late, both of which objections were properly overruled. It is very certain that no prejudice accrued to defendant from the alleged omission of allegations in the complaint, and on the evidence but one judgment could have been rendered. We think section 475 of the Code of Civil Procedure framed in accordance with section 4%, article VI, of the constitution should apply in this case. (See Vallejo & Northern R. R. Co. v. Reed Orchard Co., 169 Cal. 545 , [ 147 Pac. 238 ].)
As to the claims of J. P. M. Phillips and Bay Development Company the objections have been considered in other cases.
Finally, the claim of the San Francisco Teaming Company is attacked: First, because the complaint do.es not contain any allegation of abandonment. This objection has been previously noticed, and it was shown that other complaints contained ample allegations as to the fact as well also the answers and, besides, the findings are clear upon the point. Second, it is urged that the lien does not state the terms, time given, or conditions of the contract as shown by the contract, and there is a material variance between the lien and the evidence. (Citing California Portland Cement Co. v. Wentworth Hotel Co., 16 Cal. App. 692 , 713, [ 118 Pac. 103 , 113].) The lien states that Condon-McGlynn Company “entered into a contract on or about the 1st day of December, 1908, for labor as aforesaid, sand and material for said building with said San Francisco Teaming Company, the claimant herein, by which said labor, sand and material were furnished and the following is a statement of the terms, time given and con
Witness Donaldson, respondent’s bookkeeper, testified that there was an agreement to “supply them with sand at one dollar a load; teams at the running rate that was in existence at that time.” Later in his testimony he corrected the above statement and testified that he knew of no specific price agreed upon; that most of the details were handled through him, but that he had no recollection of the price being mentioned. The substance of this witness’ testimony was that the contractors verbally as needed ordered teams and sand and charges were made “at the running rates” — the “ordinary market running rate.” Witness Condon, one of the contractors, testified that he did not remember that there was a written contract with respondent but that the understanding was verbal; the sand was to be delivered “at so much a load depending on the haul, the minimum would be one dollar a load”; that there was no particular agreement as to the price the teams were to be paid; that the day after hauling a statement would be made and if the price “showed too high a price, it was sent back for correction”; the price payable for sand depended upon the distance it was hauled and the teams were to be paid “the current rate” and “a dollar a yard for hauling the sand a reasonable distance.” The bills from time to time were made out, as we understand the testimony, “at the running rates” for the sand and team
In the ease of Blanck v. Commonwealth Amusement Corp., 19 Cal. App. 720 , 726, [ 127 Pac. 805 ], it appeared “in some instances that no price was agreed upon,” but as it appeared that the price was the reasonable value, the omission was held not to be fatal. There is in the present case no direct and specific statement that the price was reasonable, but we think when labor is done or materials furnished at the current or going rates," or, in other words, the market rates, it may be assumed that they were reasonable in absence of any evidence to the contrary.
Section 1187 of the Code of Civil Procedure requires of the lienor that he make a statement in the notice “of the terms, time given and conditions of his contract.” The notice gave the terms as cash and, as to the time, payment was to be on delivery of the materials or performance of the labor. Pull and literal compliance with the statute would have required a statement that the price to he paid was the current or market rate at the time for the labor and materials. But as in fact this is what was "claimed, and what was understood by the parties, and would be implied as the contract in the absence of a specific agreement otherwise, we are unwilling to hold that the omission in the notice was fatal to its validity. (Barrett-Hicks Co. v. Glas, 14 Cal. App. 289 , [ 111 Pac. 760 ].)
Hart, J., and Ellison, J., pro teto., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on June 30, 1916.
Cases cited
- Olson-Mahoney Lumber Co. v. Maxwell 18 Cal. App. 668 p. 336
- Hoffman-Marks Co. v. Spires 154 Cal. 111 p. 336
- Duffy Lumber Co. v. Stanton 9 Cal. App. 38 p. 336
- C. Scheerer & Co. v. Deming 154 Cal. 138 p. 338
- G. Ganahl Lumber Co. v. Weinsveig 168 Cal. 664 p. 338
- Robison v. Mitchel 159 Cal. 581 at 591 p. 340, p. 341, p. 350
- Newell v. Brill 2 Cal. App. 61 p. 342
- Coss v. MacDonough 111 Cal. 662 p. 342
- Barrett-Hicks Co. v. Glas 14 Cal. App. 289 p. 343, p. 359
- Blanck v. Commonwealth Amusement Corp. 19 Cal. App. 720 at 726 p. 344, p. 359
- Stimson Mill Co. v. Los Angles Traction Co. 141 Cal. 30 p. 345
- Pacific Sash & Door Co. v. Bumiller 162 Cal. 664 at 667 p. 346
- Schaghticoke Powder Co. v. Greenwich & Johnsonville Railway Co. 183 N. Y. 306 p. 349
- Giant Powder Co. v. San Diego Flume Co. 78 Cal. 193 p. 349
- Johnson v. La Grave 102 Cal. 324 p. 350
- Donegan v. Houston 5 Cal. App. 626 at 632 p. 351
- Shively v. Semi-Tropic Land & Water Co. 99 Cal. 259 p. 351
- Union Lumber Co. v. Simon 150 Cal. 751 p. 352
- Wolters v. Rossi 126 Cal. 644 p. 352
- Coghlan v. Quartararo 15 Cal. App. 662 p. 352
- Davis v. Treacy 8 Cal. App. 395 p. 356
- Vallejo & Northern R.R. v. Reed Orchard Co. 169 Cal. 545 p. 357
- California Portland Cement Co. v. Wentworth Hotel Co. 16 Cal. App. 692 at 713 p. 357