Majority
On November 12, 1929, J.
On January 27, 1930, respondent filed this action against appellants, as principal and surety upon the “Materialmen’s Bond”, alleging the execution of the contract for the public improvement, the giving of the “Materialmen’s Bond”, the contract for the hiring of equipment by Harms from respondent materialman, alleging with reference to the “Materialmen’s Bond”, “that plaintiff relies particularly upon said written instrument”. Thereafter on February 24, 1930, appellants answered said complaint, which answer in addition to denying generally the material facts denied the execution of the contract executed between respondent and Harms. On the same day appellants filed their answer to the complaint, a demurrer which had been theretofore filed by appellants to the complaint was sustained. Thereafter an amended eomplant, practically identical to the original complaint save that it pleaded the contract for the hiring of the equipment by defendant Harms in its legal effect rather than in Twee verba, was filed, to which amended complaint defendants filed their verified answer on March 17, 1930, denying the contract between respondent and Harms, but admitting the execution of the “Materialmen’s Bond” and admitting also that respondent relied thereon.
Twenty-two months thereafter the case was called for trial, at which time the question of arbitration was first raised by appellants. Until the day of trial appellants had not filed
Conceding that the arbitration clause in the contract between respondent and Harms was mandatory upon those parties, under the facts and circumstances here outlined the decisive question on this appeal is whether that contract became a part of the bond executed by appellants pursuant to the Public Works Act, Statutes of 1919, page 487, as amended.
The purpose of the bond provision of the Public Works Act, we believe, was to give to materialmen and labor
In Globe Indemnity Co. v. Hanify, supra, at page 730, the court says:
“The Public Works Act was first passed in 1919, and was designed as an aid to mechanics and materialmen in the enforcement of their lien rights. Its special effort was to make the general Mechanics’ Lien Law more expansive and adaptable to actions in which the state, irrigation and reclamation districts and other large public corporations were the builders.
That it is a part of the Mechanics’ Lien Law of the state is made evident by the numerous references it makes to said law, and by the adoption of its provisions by reference. Both laws deal with the same specific subject, and are to be construed together. The legislature did not intend to defeat or embarrass the right of a lien claimant by the remedies prescribed, but meant to broaden his remedy. Two remedies pointing to the same result being open to the claimant, he may pursue either as his interest will be best served. A provision inserted in the bond by the surety, as here, in an attempt to limit the remedy a mechanic or materialman may choose to elect, would be ineffectual as an invasion of his statutory rights to adopt the remedy provided by law in a proceeding in which liberality of construction is favored. ’ ’
It has been held that the statutory materialman’s bond referred to in the above excerpt as being similar to the bond here in question creates a direct obligation, and that the bond itself affords a right of action against the principal and the surety. (General Electric Co. v. American Bonding Co., 180 Cal. 675 , 679 [ 182 Pac. 444 ]; Purington v. Olsten, 45 Cal. App. 621 [ 188 Pac. 288 ].) The action upon the statutory bond is not in any sense based upon the personal liability of the contractor but is based upon the obligation of th.e bond, since the bond provides a separate and distinct and statutory remedy. The obligation of the bond, therefore, is enforceable without reference to any contract between the contractor and the materialman. (Cooley v. Freeman, 204 Cal. 59 [ 266 Pac. 545 ]; Hub Hardware Co. v. Aetna etc. Co., 178 Cal. 264 , 266, 267 [ 173 Pac. 81 ]; Los Angeles Stone Co. v. National Surety Co., 178 Cal. 247 , 251 [ 173 Pac. 79 ]; Williams v. Tingey, 26 Cal. App. 574 [ 147 Pac. 584 ]; Holden v. Mensinger, 175 Cal. 300 , 303, 304 [ 165 Pac. 950 ]; Hazard, Gould & Co. v. Rosenberg, 177 Cal. 295 , 297 [ 170 Pac. 612 ]; Wood v. Oakland etc. Transit Co., 107 Cal. 500 , 502 [ 40 Pac. 806 ]; Martin v. Becker, 169 Cal. 301 , 306 [ 146 Pac. 665 , Ann. Cas. 1916D, 171].)
In Cooley v. Freeman, supra, the court says in speaking of an analogous situation, at pages 61 et seq.:
“The test of the liability of appellant surety hereunder is not what the rights of the contractor and highway commission are under the construction contract, but is: Did re
spondent furnish material and perform labor which was utilized in the construction work covered by the contract for public work between the highway commission and the contractor, which said work was the subject of the indemnity agreement made by appellant and sued upon herein ? There is no contention concerning the affirmative answer made by the court to this inquiry. The fact also is that the work of respondent was accepted.
“The liability of the surety is controlled by the provisions of the public work statutes of 1919, chapter 303 (Stats. 1919, p. 487), as it read in 1924, the date of the contract herein. Said statute providing for the indemnity bond thereunder read in part as follows: 1 . . . and must provide that if the contractor, person, company, or corporation, or his or its subcontractor, fails to pay for any materials, provisions, provender or other supplies, or teams, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind, that the surety or sureties will pay the same in an amount not exceeding the sum specified in the bond, and also, in case suit is brought upon such bond, a reasonable attorney’s fee, to be fixed by the court
1 ‘ There is, therefore, no escape from the conclusion that this obligation is in nowise affected by the terms of the contract between the highway commission and the original contractor, nor by a question of whether the contractor has breached his contract with the state. The obligation of the surety is to supply to persons in the class of respondent, a quick, reliable and sufficient means of payment. No lien law is available to persons performing labor or furnishing materials which go into the construction of public works. ’ ’
To hold that arbitration could be compelled as between respondent, and appellant Harms could easily have the effect of nullifying the bond, as is said in Sunset Lumber Co. v. Smith, 95 Cal. App. 307 [ 272 Pac. 1068 ], with reference to materialmen’s bonds required under sections 1184 et seq. of the Code of Civil Procedure, at page 313:
“The act of 1919 does not require that plaintiff first proceed under sections 1184 et seq. The period within which suit, may be commenced on the bond as provided in the act of 1919 shows that there need be no steps taken under sec
tion 1187 or any waiting for a pro rata payment. The act of 1919 requiring that action on the bond be. commenced within ninety days following the period within which claims of lien must be filed for record, it is obvious that if a materialman was first required to bring an action under section 1184a, a period of time would not only possibly but probably expire in excess of ninety days from the time any claims of lien must be filed for record, and, hence, the bondsmen would, by insisting upon the plaintiff first exhausting his rights pursuant to sections 1184 et seq., avoid liability for any portion of a materialman’s claim. Such construction would defeat the purpose of the act. ’ ’
The requirement of a bond in this ease is a matter of public concern and any attempt to limit, nullify or render ineffectual the bond or any of its terms would be against public policy. (Cooley v. Freeman, supra; City of Pasadena v. Charleville, 215 Cal. 384 [ 10 Pac. (2d) 745 ]; Globe Indemnity Co. v. Hanify, supra; Globe Indemnity Co. v. Barnes, (Tex. Com. App.) 288 S. W. 121 ; Standard Oil Co. v. Detroit etc. Co., 24 Ohio App. 237 [ 157 N. E. 418 ]; Hartford Accident etc. Co. v. Board of Education, 15 Fed. (2d) 317; Ingold v. City of Hickory, 178 N. C. 614 [ 101 S. E. 525 ].)
Further, we are of the opinion that upon the facts and under the circumstances of this case appellant Harms waived any right to insist upon arbitration. The laws with reference to arbitration were passed primarily for the purpose of expediting and facilitating the settlement of disputes and to overcome delays caused by litigation. They are not enacted to provide a means of creating delay (Jardine-Matheson Co., Ltd., v. Pacific Orient Co., 100 Cal. App. 572 [ 280 Pac. 697 ]; Zimmerman v. Cohen, 236 N. Y. 15 [ 139 N. E. 764 ]; Bullard v. Morgan H. Grace Co., 240 N. Y. 388 [ 148 N. E. 559 ]). Section 1282 of the Code of Civil Procedure provides the method by which arbitration may be enforced and enacts that a proceeding may be initiated by the party aggrieved filing a petition for an order directing that arbitration proceed. The default mentioned in section 1282 of the Code of Civil Procedure refers to “the failure to comply with the agreement to arbitrate”. On the facts of this case there was no showing that respondent was at any time requested to arbitrate or refused to arbitrate before within twenty-four
“But neither the agreement to arbitrate nor the submission is self-executory. A party to an arbitration agreement may breach his contract. A remedy is provided in case of his default by Arbitration Law, section 3. A party aggrieved by the failure, neglect or refusal of another to perform, either under a contract or a submission providing for arbitration, may petition the Supreme Court for an order directing that the arbitration proceed. On such an application, the other party may put in issue (a) the making of the contract to arbitrate the questions sought to be submitted to arbitration, or (b) the submission of such questions to arbitration, or (c) the failure to comply therewith ... It is only when it is found by the court that a written contract of arbitration has been made . . . covering the question sought to be included in the arbitration, and that a party is in default in the performance thereof, that the court will order the parties to the contract or submission to proceed with the arbitration in accordance with the terms thereof. ’ ’
Appellants did none of the things required by law to enforce their right to arbitrate and on the contrary filed their answer and amended answers in this action. It seems clear to us that if they ever had such right, the facts in the case at bar indicate clearly that it was waived. (Philip Bauer Co. v. Anderson Chemical Co., 206 App. Div. 423 [ 201 N. Y. Supp. 438 ]; Zimmerman v. Cohen, 236 N. Y. 15 , 18, 19 [ 139 N. E. 764 , 765].)
We find no substance in the point raised by appellants that the amended complaint of respondent did not properly allege the contract between respondent and appellant Harms but was predicated upon a common count in assumpsit. The amended complaint alleged that respondent furnished materials to Harms and that Harms used the same, promised and agreed to pay therefor an agreed price, and that the money became due and was not paid. That a contract may be pleaded in its legal effect and need not be set forth in haec
1 ‘ Besides, when the legal effect of an instrument is pleaded, and any of its conditions are omitted in the complaint, the omission is cured, if the defendant in his answer sets forth the entire contract.”
Furthermore, the action was tried upon the theory that respondent was proceeding upon an express contract and under such circumstances it has been held:
“But in any view of the case defendants suffered no injury. The trial was had upon the issues arising out of the contractual relations of the parties, and whether we call the contract an express or an implied one we cannot see that defendants were injured by any variance between averment and proof.” (Gibson v. McReynolds, 175 Cal. 263 , 268 [ 165 Pac. 921 , 923].)
The finding of the court as to the amount due under the contract by Harms to respondent is amply sustained by the evidence and requires no discussion in detail.
The judgment is affirmed.
Houser, Acting P. J., and York, J., concurred.
A petition by appellants to have the cause heard in the Supreme Court, after judgment in the District Court of Appeal, was denied by the Supreme Court on August 19, 1935.
Cases cited
- Peterson v. Freiermuth 17 Cal. App. 609 p. 737
- Avery v. Clark 87 Cal. 619 p. 737
- William H. Birch & Co. v. Magic Transit Co. 139 Cal. 496 p. 737
- Humboldt Lumber Mill Co. v. Crisp 146 Cal. 686 p. 737
- Cooley v. Freeman 204 Cal. 59 p. 737, p. 738
- Williamson v. Egan 209 Cal. 343 at 344 p. 737
- Continental National Bank of Los Angeles v. Republic Casualty Co. 202 Cal. 586 at 589 p. 737
- Sunset Lumber Co. v. Smith 95 Cal. App. 307 p. 737, p. 739
- Globe Indemnity Co. v. Hanify 217 Cal. 721 at 730 p. 737
- Fidelity & Deposit Co. of Maryland v. United States 187 U. S. 315 p. 737
- General Electric Co. v. American Bonding Co. of Baltimore 180 Cal. 675 at 679 p. 738
- Purington v. Olsten 45 Cal. App. 621 p. 738
- Hub Hardware Co. v. Aetna Accident & Liab. Co. 178 Cal. 264 at 266, 267 p. 738
- L.A. Stone Co. v. Nat'l Sur. Co. 178 Cal. 247 at 251 p. 738
- Williams v. Tingey 26 Cal. App. 574 p. 738
- Holden v. Mensinger 175 Cal. 300 at 303, 304 p. 738
- Hazard, Gould & Co. v. Rosenberg 177 Cal. 295 at 297 p. 738
- Wood v. Oakland & Berkeley Rapid Transit Co. 107 Cal. 500 at 502 p. 738
- Martin v. Becker 169 Cal. 301 at 306 p. 738
- City of Pasadena v. Charleville 215 Cal. 384 p. 740
- Jardine, Matheson & Co. v. Pacific Orient Co. 100 Cal. App. 572 p. 740
- In re Zimmerman 236 N. Y. 15 at 18, 19 p. 740, p. 741
- In re the Arbitration between Bullard & Morgan H. Grace Co. 240 N. Y. 388 p. 740
- Antonelle v. Kennedy & Shaw Lumber Co. 140 Cal. 309 at 321 p. 742
- Gibson v. McReynolds 175 Cal. 263 at 268 p. 742