1. Pleading—Variance of Proof—Dismissal of Complaint.There can be no doubt from the complaint—and the position was emphasized by an admission, of plaintiff’s counsel during the examination of the witness Schildwachter—that the action was to recover upon a quantum meruit for the reasonable value of the work and material furnished by Kierst, not for.damages for breach of contract. But the proof did not conform to the pleading and admission. No detailed evidence was given of the work and
The plaintiff's whole claim is based upon an erroneous view of his position at the time he was stopped. Kierst agreed to complete the work “on or about the 20th day of March, 1885.” He testifies that he was expelled the latter part of April, or beginning of May; the defendant, that it was on April 14th. In either case it was over three weeks after the work should have been turned over, complete, to the defendant. Ho excuse for this delay, having any substance, is given. The defendant was not to blame in any way; and the plaintiff, with great philosophy, treats it as one of the necessary evils which an owner is compelled to put up with when he enters into a building contract. It is impossible, however, for the law to overlook this breach with the same easy good nature. If the provision of the contract as to time is to be overlooked, it must be because the case falls within that narrow class where courts have always held time not to be of the essence of the contract. On this head, Parsons says:
“The court will always inquire into the time when a thing is to he done, as they will into any other part of the contract. If it seems that the whole value or a material part of the value of the transaction depends upon its being done at a certain time, and no other, or that the substitution of any other will subject him [one of the contracting parties] in any way to loss or material inconvenience, then
time is certainly of the essence of the contract, so far as he is concerned, and the court will so regard it.” 3 Pars. Oont. side pages 384r-386.
Most certainly, this case is of the class thus referred to. The defendant testified, without contradiction, that she saw the delay would result in her not being able to rent the building when the season came. But it required no such testimony to show that time was here of the essence of the contract. It was manifest from its very nature that delay meant loss of rents.
Nor did the defendant waive her right thus to terminate the contract. It appears that she did not expel Kierst at once when he ran over his time. But this cannot be construed into a consent that he might go on, in any event, until he should get the work done. An owner may be willing to wait for a brief period, without being willing to wait indefinitely. The continued failure on the contractor’s part to complete the work is a continuous breach of the contract, of which the owner may avail himself at any time. To hold otherwise would put the owner completely at the mercy of a dilatory contractor. We do not mean to intimate that the owner may induce the contractor to continue work under the belief that the contract is still in existence, and then refuse to pay him for the work so done. We are not here concerned with the work already done. The question presented by the plaintiff’s claim now under consideration is whether Kierst had the right to remain and finish his work; and we must hold that he had not. Having failed to complete when he agreed to, the defendant had the right to make him give way to speedier contractors. Thus, the plaintiff failed to show a right to recover the contract price of $5,200, and the whole basis upon which the referee made his award is erroneous. As the plaintiff insisted upon recovering the contract price, the defendant was justified in demanding proof that his assignor had earned that sum in accordance with the terms of the contract. She made such a demand at the proper time, and in the proper manner.
If the plaintiff seeks to recover upon a quantum meruit, he must prove what it was he did, which was not paid for under the contract, and its value. He cannot throw upon the defendant the burden of showing what he omitted. Nor can he escape this result by contending that the full contract price shall represent the reasonable value of the contract work. It is no evidence whatever of-such value. Gumb v. Railway Co., 114 N. Y. 411 , 21 N. E. 993 ; Kennedy v. McKone (Sup.) 41 N. Y. Supp. 782 . He cannot evade a heavy burden of proof by calling his action one thing when it is in fact another. Though he sued upon a quantum meruit, his proof was for a recovery under the contract; and, by the course of the trial, this cause of action became practically substituted for the other. Nor was its nature changed by the concession that the defendant might cut down the amount, so far as she could, by proof of the value of the uncompleted work. The plaintiff could not thrust this concession upon the defendant, and take in exchange, against her will, the right to call the contract price of $5,200 the prima facie value of the work done. It is true that considerable laxity has
As the judgment must, for the reasons stated, be reversed, it becomes unnecessary to consider the second cause of action, upon the Morgan claim, as to which the evidence and findings may be entirely different upon a new trial.
The judgment should be reversed, the order of reference vacated, and a new trial ordered, with costs to the defendant to abide the event. All concur.