Majority
Headnote
1. Building Contract — Implied Obligation op Owner — Responsibility for Acts of Architect. °The complaint alleges two causes of action. The first cause of action was for the balance due under a certain contract for excavating the cellars and foundation for a building to be erected upon the property of the defendant, it being alleged that there was due and unpaid under the contract the sum of $10,-792.50. The second cause of action was to recover damages sustained by the plaintiffs in consequence of the defendant having “hindered, delayed, embarrassed, and interfered with them [the plaintiffs], and with the work being carried on by them; prevented the plaintiffs from going on and finishing the same in a reasonable and proper manner; suspended the entire work under said contract from time to time; forced them to keep their working forces, teams, and machinery idle for a long period of time; filled or caused to be filled the area of excavation with timbers and braces, so that access to the said work with teams was prevented; forced the plaintiffs to take out the material excavated by derrick and buckets instead of by teams; caused the plaintiffs to lose the sale of the material excavated by inability to deliver at time agreed upon; forced the plaintiffs to handle and rehandle many times the excavated material before removing the same; increased the time and necessity of pumping beyond that called for in the contract; and in many other ways increased the expense of plaintiffs’ work,”—whereby it is alleged that the plaintiffs sustained damages in the sum of $73,800. The referee found that there was unpaid and due to the plaintiffs on account of the contract price which the defendant agreed to pay for such excavation the sum of $7,500, and for extra work done by the plaintiffs in the sum of $485. Upon the second cause of action the referee found that for various periods of time during the year 1892 the plaintiffs’ work of excavation was entirely suspended, either by order of the architect or in consequence of the said premises being so occupied by other contractors acting under the architect’s supervision and direction that the plaintiffs were unable to have access to the premises for the purposes of their contract; that the whole number of days that the plaintiffs were prevented from prosecuting their work was forty-seven; that the said interruptions to the plaintiffs’ work were unreasonable, and the fault of the defendant, and in disregard and violation of the duty which the defendant owed to the plaintiffs to give them fair access to the said premises, in order that they might perform their contract, and not to hinder or obstruct them in their work. The referee also found that in
It is quite evident, I think, that the correctness of the referee’s decision depends upon the question as to whether the finding that the interruptions to the plaintiffs’ work were caused by the defendant, and were a violation of the duty under which, or implied contract whereby, the defendant was to furnish access to the said premises, in order that they should perform their contract, and not to hinder and obstruct them in their work, was sustained by the evidence. In considering this question it is quite important to consider how far the action of the architect, under the contract between the plaintiffs and the defendant, was as agent of the defendant, and how far the architect, in giving directions to the plaintiffs as to the manner of doing the work, and in directing and controlling the other contractors, in the performance of their contracts, to so unreasonably and unnecessarily obstruct the work" of the plaintiffs as to materially increase the cost of performing their contract, can be said to be acting for the defendant. There can be no question but that under this contract there was an “implied understanding. on all parties that they [the plaintiffs] were to be unrestricted in the employment of means to perform it [the contract], and that nothing which it was the duty of the owner to do to enable the contractors to perform should be left undone” (see Mansfield v. Railroad Co., 102 N. Y. 213 , 6 N. E. 386 ); and the question is whether there has been a breach by the defendant of this implied understanding or contract. It is not claimed by the plaintiffs that the defendant in any way directed or interfered with the operation of the work, or with the performance by the plaintiffs of their contract, except so far as the directions given by the architect to the plaintiffs and to the other contractors. And we must look to the contract to determine just what relation this architect bore to the parties to the contract, and to the evidence to see just how far either party was responsible for an unreasonable or negligent performance of the duties imposed upon him. In the case of Mansfield v. Railroad Co., supra, attention is expressly called to the absence of any provision in the contract for the submission of the question there at issue to
“It was made the duty of the owner not only to prepare the foundations for the reception of the work of the contractors, but also to notify them [the contractors], through their agent, of the fact of such readiness. The terms of the contract plainly imply that the notice was to be of an actually existing condition, and not the expression of an opinion on the part of the engineer that the foundations were sufficiently advanced to enable the contractors to prosecute their work advantageously. The contractors have not submitted any such question to the decision either of the owners or their engineer, and, in view of the heavy obligations assumed by them, it would have been unwise and hazardous to have done so.”
We have here to ascertain just what questions were left to the decision of the architect by the contract, and how far the architect, in determining the questions submitted to him, was acting as the chosen arbitrator between the parties independently of either party, but upon his own responsibility. By this contract both parties agree that the architect shall have a certain limited control over the work; that the contract itself shall be performed in a good workmanlike and substantial manner, to the satisfaction and under the direction of the said architect, to be testified by the writing of a certificate under the hand of the said architect; and his certificate is as binding upon the defendant as upon the plaintiffs. In determining whether or not the work has been so completed, he certainly would not be "acting as agent or representative of the defendant any more than of the plaintiffs. As to both, he occupied under the terms of the contract the same position,—as a person to whom was referred the determination of the question as to the completion of the contract according to its terms,—and his determination upon that question was clearly to be binding upon both parties in the absence of fraud or palpable error or mistake. The plaintiffs were “also to dig down the banks along and away from the curb and stoop lines, including along adjoining courtyards, to such extent so as to allow for proper sheet piling and placing foundations the full depth of banks.” Then appears the express provision by which the excavation" “shall be arranged and attended to as directed by the architect, and to be finished so as to enable the mason to start walls and foundations not later than forty-five working days, beginning from date of original contract, dated on or about October 15, 1891”; and the plaintiffs were to prepare their work on the banks so as to enable the contractor for sheet piling properly to attend to his part of the work. Then comes the provision: “At all such points where both contractors are required to work, the number of excavations shall be attended to as is customary for such class of work, and as otherwise and finally directed by the architect.” Then, as contemplating a clashing of contractors which would delay the plaintiffs in the performance of their contract beyond the time specified, provision is made for an extension of time to allow for such delay, and the architect is called upon to adjust and arrange for the proper allowance of such extra time. The fact, important to be considered, that it was contemplated by the contract that the plaintiffs were to carry on their contract contemporaneously with other contractors
“I am the Albert Wagner who drew these specifications in this contract we have talked about here. I am the architect in that contract. I had the superintendence and charge of the excavation at the Bowery, the Third Avenue Bail-road power house, on the part of the Third Avenue Bailroad people.”
It thus appears that this architect had charge of this work on behalf of the company, and was paid by the company an architect’s fee for his services; and to that extent he was in the employ of the defendant, and paid for the services which he rendered for it.
It is now too well settled in this state to be questioned that, where the parties have selected an arbitrator, who is to determine the questions that arise during the performance of the contract, and upon whose certificate the payments are to be made, and it is provided in the contract that the determination of such arbitrator is to be binding upon them, his determination is a condition precedent to the right of either party to recover under the contract, and that, in the absence of fraud or palpable mistake, his certificate is final.
In the case of McMahon v. Railroad Co., 20 N. Y. 466 , where the provision was that “the work shall be executed under the direction and constant supervision of the engineer of the company, by whose measurements and calculations the quantities and amounts of the several kinds of work performed under this contract shall be determined, and who shall have full power to reject or condemn all work or materials which, in his opinion, do not fully conform to the spirit of this agreement, and shall decide every question which can or may arise between the. parties relative to the execution thereof, and his decision shall be final and binding upon both parties,” it was held that, although the engineer who makes the contract was the employé of the defendants, selected by and receiving compensation from them, his decision was not unlike that of an arbitrator; with this difference; that he is the selected and paid servant of one of the parties. But still his certificate, if legally made, is absolutely conclusive upon the rights of the contractor to recover, such contractor being dependent entirely upon the skill and integrity of the company’s agent.
In Byron v. Low, 109 N. Y. 294 , 16 N. E. 45 , where the provision in the contract was that his (the chief engineer’s) determination was final and binding upon both parties, the court said:
“Under this provision, the certificate of the engineer became a condition precedent to the plaintiff’s right of action. The chosen arbitrator was to fix the amount of the final payment.”
“This case, therefore, is unlike those, so frequently arising, in which the certificate or estimate is required from an architect or engineer in the employment of one of the parties. In that class of cases the danger that the person acting as an arbitrator might favor his employers is obvious. While neither natural” nor legal disabilities hinder a person from being an arbitrator, provided the fact is known to the parties at the time of the submission, still, as he is the agent of both parties alike, and impartiality is the fundamental requisite, the courts closely scrutinize the action of an arbitrator whose relations to one of the parties was such as to naturally influence the judgment even of an honest man.”
We thus have the rules which are to be applied in considering the responsibility of the parties for the acts of the architect. •
By the third and fourth clauses of the contract, as before stated, any payment to the plaintiffs under the contract was conditioned upon the certificate of the architect as to the performance of the contract. By the ninth clause it is expressly provided that, in determining any dispute respecting the true meanings of the drawings or specifications, the decision of the architect shall be final and conclusive. The position that the architect held under these provisions undoubtedly would be that of the arbitrator selected by both parties ; and it is quite clear, I think, that in the absence of bad faith or palpable mistake his decision would be binding, and neither party would be responsible to the other for any damages sustained in consequence of his neglect or fault in making a decision. When we come, however, to his act in directing how the work should be done, and in providing for the sand that should be retained, for the manner in which the excavation should be made, and for the manner in which the plaintiffs were to perform their work jointly with the other contractors, there is no provision as to his decision being binding upon the parties; nor does it appear that as to such directions he represented both parties. It is quite evident that he did not consider himself as representing the plaintiffs, for he testifies that he “had the superintendence and charge of the excavation at the Bowery, the Third Avenue Railroad power house, on the part of the Third avenue people”; and he was paid by the defendant. It thus appears that the contract itself draws a distinction between the decision of the architect, as arbitrator, in determining any dispute respecting the true meanings of the drawings and specifications, and the action of the architect in directing the method and conditions under which the work should be performed. That a person can, under a contract of the same character as the one in question, occupy two positions towards the parties,—one as an arbitrator to decide-certain specific questions as they arise, and the other as representing, as to other questions arising between the parties, one of the parties to the contract,—seems to be settled by authority. In the case-
The claim is made that the defendant is not responsible for the delay caused by Hughes, the person who had the first contract to do the shoring, because it did not appear that Wagner, as the defendant’s agent, had control of Hughes. We think the whole testimony of Wagner, however, shows that he did have control of the work under Hughes’ contract. He testifies that he had charge of the excavation on behalf of the railroad, and had complete charge and superintendence of the work personally during the whole construction, and that he expressly instructed the plaintiffs that where-ever Hughes wanted them.to stop they were to stop. “I directed Del Genovese & Towle to stop and await the convenience of Mr. Hughes in fixing the braces. I did tell them to work with him.” And he testified that when Galligan. came on the work, he did the same thing with Galligan, and that he told the plaintiffs to stop whenever Galligan wanted them to stop. So in regard to the masons. His .instructions to the plaintiffs constantly were to do whatever the masons directed them to do. His whole testimony shows that he had entire charge of the work, and did, as a fact, direct all the contractors in the performance of their contracts, and that he was responsible to the defendant for the manner in which the work was done. I cannot see, however, how it is material in determining a question as to a violation by the defendant of its duty or obligation to give to the plaintiffs their reasonable access to the premises, to enable them to perform their contract, whether Wagner had control over Hughes or not.. It certainly would not be a performance
As to the amount allowed for damages, it would appear that it was quite reasonable, and much less than the testimony would have-justified.
We also agree with the referee that the provision of the contract allowing the architect to adjust and arrange a proper allowance for-any loss of time by which the contractor should be delayed on account of other contractors is no defense to the claim of the plaintiffs to be paid the damages sustained by reason of the unreasonable or improper act of the defendant in violating its agreement with them. It does not appear that the architect acted under this provision of the contract; but, if he had, it is clear that the only object of the provision was to extend the time for the completion of the contract by the plaintiffs in case of such a delay caused by the other contractors in the proper performance of their work. Two cases are cited,—Haydnville Min. & Manuf’g Co. v. Art Institute, 39 Fed. 484 , where, under a somewhat similar provision in a contract, the defendant’s contention was adopted; and Nelson v. Associated Co., 30 El. App. 333, where the contrary view was taken. We agree with the referee that the latter case should be followed. We also agree with the referee as to his disposal of the defendant’s counterclaim upon the ground stated by him, and do not think that it requires any further discussion.
The judgment should be affirmed, with costs. All concur.