Majority
Headnote
1. Municipal Contracts—Construction—Monthly Payments.This action has been twice tried. On the first trial the referee held that the defendant was not required by the contract to pay on the 10th day of each month 90 per cent, of the value of all materials furnished and labor performed during the preceding month, but was bound to pay only 90 per cent, of the value of such work as had been fully completed, and of materials used in completed work. The referee also held that the provision in defendant’s proposals, “The vitrified pipe line is mostly, and the tunnels are entirely, to be in soft shale rock,” was not binding on the defendant. On an appeal to the general term it was held that these constructions of the contract were erroneous, and a new trial was granted. 77 Hun, 124 , 28 N. Y. Supp. 440 .
The contract provided:
“The party of the first part [the defendant], agrees that their executive committee will cause an estimate to be made before the tenth day of each month of the value of the labor and materials on all work completed up to the first day of the same month, and will on said tenth day of each month pay to the party of the second part [the plaintiff], as a partial payment, 90 per cent, of the contract price of such completed work.”
The referee before whom the trial now under review was had followed the rule laid down by the general term,—that the plaintiff was entitled to be paid on the 10th day of each month 90 per cent, of the value of materials furnished and work performed during the preceding month,—and decided, as a question of fact, that the defendant had failed to perform this stipulation in the contract. The decision of the general term upon this clause of the contract is sought to be reopened in this court. It seems to me that this construction of this clause, which is quite indefinite, is the only one which is permissible. Under the defendant’s theory, in case a large amount of iron pipe had been delivered on the works, or one of the reservoirs had been nearly completed, the contractor would not be entitled to any advance, because the reservoir was not completed and the iron pipe in place. This clause should be construed with reference to the well-known and uniform practice under such contracts; that is, that the contractor is entitled to his percentage upon the value of his work done and materials furnished during the preceding month. I think the general term correctly construed this clause in the contract; and, this being the correct construction, it is not contended by the defendant that it had paid monthly the amounts to which the plaintiff was entitled.
In July, 1889, the plaintiff began the construction of the principal, or “Kent,” reservoir, and shortly afterwards was stopped by the owner of the fee of the land upon which the reservoir was to be constructed, because the village had not acquired title to the land; and for more than a month labor was suspended upon that part of the work, because the title had not been acquired, which was solely the
The learned referee held that by reason of the defendant’s failure to pay monthly 90 per cent, of the value of the work done and materials furnished during each preceding month, and by its delay in acquiring title to the land for the Kent reservoir, and because the excavations for the vitrified pipe line and the tunnels were in hard instead of in shale rock, the plaintiff was excused for not completing his contract by the 1st of December, 1889. Aside from the failure to complete the work within the time contracted, the referee found that the plaintiff had failed to lay several hundred feet of the pipe lines six feet below the surface, and that by reason thereof the defendant was damaged to the extent of $2,000, which sum the referee deducted from the amounts found due the plaintiff for work done and materials furnished. Both parties having broken the contract, and the defendant’s breaches being a perfect or partial.excuse for the plaintiff’s failures, the latter’s breaches are not a complete defense to his action to recover the value of labor performed and materials furnished. A
It is not urged in behalf of the defendant that the referee erred in the admission or rejection of evidence, and I am of the opinion that the defendant has failed to demonstrate that the referee has erred to the prejudice of the defendant, and that its appeal cannot be sustained.
But a single question is urged in support of the plaintiff’s appeal, which is that the referee erred in not allowing him interest on all or some of the items making up the sum recovered. The case does not show that the defendant has collected the plaintiff’s certified check for $2,000, deposited by the plaintiff as security for his performance of the contract; and, in the absence of such evidence, the plaintiff is not entitled to interest on that item. The other items making up the recovery were unliquidated. Neither the quantities of the work performed, nor the quantities of materials furnished, for which the prices were agreed on, had been ascertained, nor could they be readily ascertained, by the defendant; and, the amount when ascertained, was subject to a reduction for damages sustained by the defendant for improper performance by plaintiff of some of the work; and the amounts due for extra work, for which prices were not agreed on, were clearly unascertainable without taking evidence. The claims recovered by the plaintiff were unliquidated. Mansfield v. Railroad Co., 114 N. Y. 331 , 21 N. E. 735 , 1037; Gray v. Railroad Co., 89 Hun, 477 , 35 N. Y. Supp. 378 , affirmed in 157 N. Y. 483 , 52 N. E. 555 . I think no error was committed in refusing to allow the plaintiff interest on the several items included in his recovery.
The judgment is affirmed, without costs to either party, as both have appealed, and neither has succeeded. All concur.
Cases cited
- Mansfield v. New York Central & Hudson River Railroad 114 N. Y. 331 p. 281
- Gray v. Central Railroad 157 N. Y. 483 p. 281