Majority
Headnote
1. Building Contract—Installments—Recovery—Architect’s Certificate.The action was brought to foreclose a mechanic’s lien. The complaint was dismissed without costs. Both parties appeal,—the plaintiff from so much of the judgment as dismissed the complaint, and the defendant from so much as refused costs to her. The plaintiff contracted to put up a building for the defendant’s testator at a certain price, to be paid in installments. It was provided in the contract that a certificate should be obtained from and signed by the architect before an installment should become payable. The action was brought to recover the last installment. The plaintiff alleged full performance of the contract. That was denied by the defendant. There was a serious conflict of evidence as to whether the certificate had been procured from the architect, entitling the plaintiff to recover the last installment; the plaintiff insisting and giving evidence that the certificate had been given, and the architect testifying that he did not think he gave a certificate, and that it had never been asked for. Upon that issue the referee found for the defendant, and dismissed the complaint. The plaintiff was bound to produce the certificate before he was entitled to his payment, and that certificate was a condition precedent to his right to be paid in full. Until he produced it, he was not entitled to recover. Weeks v. O’Brien, 141 N. Y. 199 , 36 N. E. 185 . The finding of the referee was sustained by the evidence. Therefore his dismissal of the complaint was correct. But the failure to obtain a certificate did not take away permanently the right of the plaintiff to be paid whatever was due to him upon the contract. When that certificate shall have been obtained, the defect in his cause of action will be supplied. The determination of the referee was not, therefore, an adjudication that the plaintiff could never recover, but was simply a determination that the bringing' of the action had been premature, and amounted in effect to a nonsuit. The complaint should not, therefore, have been dismissed absolutely, and the judgment should be modified to read that the complaint was dismissed, but “not upon the merits.” The question of costs was within the discretion of the referee, and, upon the whole case, we see no reason for interfering with the manner in which he exercised it. The defendant’s appeal should therefore fail.
The judgment should be modified by inserting after the word “dismissed” the words “but not upon the merits,” and, as so modified, be affirmed, with costs to the respondent. All concur, except O’BRIEN, J., who dissents.
(dissenting). The complaint was silent as to whether the architect’s certificate was or was not given, and although that issue was presented by the answer, and met by the reply, it was one to which the referee gave undue importance, by deciding the case on that point alone. During the work, although the contract provided at different stages thereof for eight separate certificates, it appears that, exclusive of the final one, in dispute, there were but three given, and that, regardless of their presentation, payments were made by the defendant. It will be noticed, there
Dissent
“We think, this issue as to the completion oí the work by the defendant having been opened by the counsel for the defendant, and it appearing from his evidence that no certificate was necessary to enable the plaintiff to recover the difference between the last installment and the amount expended by the defendant in completing the work, the complaint should not have been dismissed upon the ground upon which the motion was granted, but that the case should have gone to the jury upon the question so litigated.”
It is urged, however, that the lien was filed and the suit begun before the completion of the work, and was therefore premature. But this was not conclusively established, there being evidence on
Cases cited
- Weeks v. O'Brien 141 N. Y. 199 p. 567, p. 569