Majority
Headnote
1. Mechanics’ Liens—Default by Contractor—Liability op Owner to Material Men.The defendant Stoll was the owner of certain prem-Ises situate at the northeast corner of 170th street and Broadway, in the borough of Manhattan. On these premises he erected a seven-story apartment house, of modern character; and in connection with such erection he entered into a contract with Kelley and Waterbury, ■composing the firm of E. Kelley & Co., to do all the plaster work in such building. The last-named firm contracted with the plaintiff, Person, and the defendant Getler, to furnish a part of the material necessary in the performance of their contract, which the said parties furnished. Person and Getler, not being paid in full for the .material so furnished, filed liens upon the premises therefor. Kelley and Waterbury, claiming that the defendant owner had been guilty of a breach of contract, elected to rescind the same, and thereafter also filed a mechanic’s lien for the amount which they claimed to be due and unpaid to them under the contract. This action is brought by the plaintiff, Person, to foreclose his lien; and he made as parties thereto the subsequent lienors, Getler and Kelley and Waterbury. The defendant owners procured the lien to be discharged,
It is claimed by the appellants that such claims are so defeated! for the reason that the right to a judgment of foreclosure and sale.' and for the deficiency judgment depends upon the fact of the right of Kelley and Waterbury to maintain their right to a lien. We do not think that such result' necessarily follows. The trial court found, and, as we think, upon sufficient' evidence for that purpose, that there was a substantial performance by Kelley and Waterbury of their contract, and that the defendant owner was guilty of a breach of the contract. Under such circumstances, the defendant owner became liable for the payment of the claims of the material men, if there remained due and unpaid sufficient of the contract price to discharge-such claim; and this would be so even though there were a breach-of contract upon the part of Kelley and Waterbury, and the defendant owner had gone on and completed the building, if, under such circumstances, there remained a sufficient part of the contract priceundisposed of to pay the same, deducting therefrom the cost of completion of the contract. Mack v. Colleran, 136 N. Y. 617 , 32 N. E. 604 . In the present case the evidence tended to establish, and the court found, that the cost of performance of the contract at the time when Kelley and Waterbury elected to rescind the same was only the sum of '$64, and the amount due and unpaid thereon was more.than sufficient to discharge the lien of Person and Getler. Consequently these parties are clearly entitled to the judgment which has-been rendered in their favor, even though Kelley and Waterbury ought to have been defeated in the claim which they made. It follows, therefore, that, so far as Person and Getler are concerned, the-decree and judgment should be affirmed.
The rights of Kelley and Waterbury rest upon different considerations. By the answer which they interposed, and which is to be treated as the complaint, as between the owner and surety and themselves, so far as is material, there is set up the contract to do the plastering work and furnish the material at an agreed price of $10,164. It then avers that they proceeded with the work and furnished the-materials as provided by the contract, and that there was due and! owing to them, oyer and above all payments made, the sum of $2,-070.75, and that they also performed extra work to the value of $200.25, for which they have not been paid. They further aver that they did not perform all the work and labor or furnish all of the material for the completion of the contract for the reason that the-owner failed and neglected to perform his part of the contract, by refusing to pay in accordance with its terms; that they then elected to, and did, rescind such contract; filed their lien for the unpaid
As we have before observed, the court found, upon sufficient evidence to sustain the findings, that Stoll and Waterbury substantially performed their contract according to its terms, and, in order to complete the same, the owner was only required to expend therefor the sum of $64. It is evident from the averments contained in the answer of Kelley and Waterbury that the contract price no longer furnished the measure of the sum which they were entitled to recover as against the defendant owner and the surety company. When they elected to rescind their contract, they were remitted in their right to recover on the basis of a quantum meruit for the reasonable value of the work done and the materials furnished. Fox v. Davidson, 36 App. Div. 159 , 55 N. Y. Supp. 524 . It was within their right to perform the contract, and then bring their action to recover the contract price. Wharton & Co. v. Winch, 140 N. Y. 287 , 35 N. E. 589 . They cannot now, however, avail themselves of this rule, as they elected to rescind, and therefore became relegated, as matter of strict right, to alone recover upon the basis of a quantum meruit.
It is the claim of the appellant (and such contention is supported by the facts appearing in the record) that there was no evidence which proved, or tended to prove, aside from the contract, what was the reasonable value of the work, labor, and services, and materials furnished, which were done by Kelley and Waterbury. The course which the trial took upon this subject was somewhat novel. Kelley and Waterbury, to make out their case, proved the contract in which the contract price appeared, and the installments to be paid as the work progressed. They then proceeded to prove the amount and number of payments falling due; the failure of the defendant owner to make payment as the contract required; the sums paid under the terms of the contract; the notes given in part payment by the defendant owner; and the amount received upon such notes; and taking all of the payments together, and the amount realized upon the notes, and deducting the aggregate sum from the contract price agreed to be paid, they claim to have arrived at the amount represented by their lien, and thereby established the ■ sum for which they were entitled to a decree of foreclosure, and for the deficiency judgment. The claim for extra work is excluded in this case, as the court disallowed such claim; and properly so, we think. In any event, no appeal has been taken which involves such question. It is needless, therefore, to consider it. The court, in arriving at its conclusion, adopted these figures, deducted therefrom the sum of $64, and awarded the decree and judgment for the balance. It is evident, therefore, that this proceeding did not conform with the requirements of the law governing such subject. Although the appellant calls our attention to this error, and makes it the basis upon which he asks for a reversal, it is clearly evident that he is in no position to take advantage of it. During the whole course
There is a further claim that the contractors at no time procured any architect’s certificate, for which the contract provided. The proof was abundant, however, to show that all of the parties waived performance in this respect, and the court has so found.
The judgment should therefore be affirmed, with costs to the plaintiff and to the defendants Getler and Kelley and Waterbury. All concur.
Cases cited
- Mack v. Colleran 136 N. Y. 617 p. 325
- Fox v. Davidson 36 App. Div. 159 p. 326
- William Wharton, Jr., & Co. v. Winch 140 N. Y. 287 p. 326
- Lahr v. Metropolitan Elevated Railway Co. 104 N. Y. 268 p. 327