← Historical versions

Versions of s. 45(3)

N-7 — National Energy Board Act · 1 version

Historical text comes from the Justice Laws point-in-time corpus and is unofficial — not the official version.

  1. 2002-12-31 to present available View Source

    The Board may exempt a company from all or any of the provisions of this section where the deviation, change or alteration was made or is to be made for the purpose of benefiting a pipeline, or for any other purpose of public advantage, as may seem to the Board expedient, but the deviation, change or alteration shall not exceed such distance as the Board requires from the centre line of the pipeline, located or constructed in accordance with the plans, profiles and books of reference approved by the Board under this Act.