← Historical versions

Versions of s. 48.13(1)

N-7 — National Energy Board Act · 1 version

Historical text comes from the Justice Laws point-in-time corpus and is unofficial — not the official version.

  1. 2016-06-19 to present available View Source

    A company that is authorized under this Act to construct or operate a pipeline shall maintain the amount of financial resources necessary to pay the amount of the limit of liability referred to in subsection 48.12(5) that applies to it or, if the Board specifies a greater amount, that amount.