Versions of s. 48.15

N-7 — National Energy Board Act · 1 version

Historical text comes from the Justice Laws point-in-time corpus and is unofficial — not the official version.

  1. 2016-06-19 to present available View Source

    If an unintended or uncontrolled release of oil, gas or any other commodity from a pipeline occurs, the Board may order the company that is authorized under this Act to construct or operate that pipeline to reimburse any federal, provincial or municipal government institution, any Aboriginal governing body or any person the costs and expenses that the Board considers reasonable that they incurred in taking any reasonable action or measure in relation to the release even if the costs and expenses are more than the amount of the limit of liability referred to in subsection 48.12(5) that applies to that company.