    Where a Canadian carrier or distribution undertaking cannot, on terms acceptable to it, obtain the consent of the municipality or other public authority to construct a transmission line, the carrier or distribution undertaking may apply to the Commission for permission to construct it and the Commission may, having due regard to the use and enjoyment of the highway or other public place by others, grant the permission subject to any conditions that the Commission determines.